74-343 · Question #60
You are a project manager for a large telecommunications company that uses Project Professional 2013. The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the…
The correct answer is B. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for. See the full explanation below for the reasoning.
Question
You are a project manager for a large telecommunications company that uses Project Professional 2013. The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the entire project and not for an individual task. You need to add the fixed cost of S 150,000 to your schedule and spread it across the duration of the project. What should you do?
Options
- AIn the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
- BIn the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
- CIn the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
- DIn the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
How the community answered
(23 responses)- A9% (2)
- B74% (17)
- C4% (1)
- D13% (3)