You are a project manager for a large telecommunications company that uses Project Professional 2013. The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the…

The correct answer is B. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for. See the full explanation below for the reasoning.

Question

You are a project manager for a large telecommunications company that uses Project Professional 2013. The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the entire project and not for an individual task. You need to add the fixed cost of S 150,000 to your schedule and spread it across the duration of the project. What should you do?

Options

  • AIn the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
  • BIn the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
  • CIn the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for
  • DIn the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    74% (17)
  • C
    4% (1)
  • D
    13% (3)