Microsoft
74-343 · Question #24
Your company uses Project Professional 2013. You are scheduling two tasks. One task is named Test Solution, and the other task is named Create Solution Test Plan. You want the Test Solution task to…
The correct answer is D. Create a Finish to Start predecessor relationship from the Create Solution Test Plan task to. See the full explanation below for the reasoning.
Question
Your company uses Project Professional 2013. You are scheduling two tasks. One task is named Test Solution, and the other task is named Create Solution Test Plan. You want the Test Solution task to start three working days after the finish date of the Create Solution Test Plan task. You need to set up a dependency between these two tasks. What should you do?
Options
- ACreate a Start to Start predecessor relationship from the Create Solution Test Plan task to
- BCreate a Start to Start predecessor relationship from the Test Solution task to the Create
- CCreate a Finish to Start predecessor relationship from the Test Solution task to the Create
- DCreate a Finish to Start predecessor relationship from the Create Solution Test Plan task to
How the community answered
(32 responses)- A19% (6)
- B3% (1)
- C9% (3)
- D69% (22)
Community Discussion
No community discussion yet for this question.