Your company uses Project Professional 2013. You are scheduling two tasks. One task is named Test Solution, and the other task is named Create Solution Test Plan. You want the Test Solution task to start three working days after the finish date of the Create Solution Test Plan task. You need to set up a dependency between these two tasks. What should you do?
Options
- ACreate a Start to Start predecessor relationship from the Create Solution Test Plan task to
- BCreate a Start to Start predecessor relationship from the Test Solution task to the Create
- CCreate a Finish to Start predecessor relationship from the Test Solution task to the Create
- DCreate a Finish to Start predecessor relationship from the Create Solution Test Plan task to