nerdexam
Microsoft

74-343 · Question #22

74-343 Question #22: Real Exam Question with Answer & Explanation

Sign in or unlock 74-343 to reveal the answer and full explanation for question #22. The question stem and answer options stay visible for context.

Question

You are a project manager who uses Project Professional 2013. After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the original scheduled dates. You need a graphical view that shows the current schedule to baseline. Which view should you use?

Options

  • ADetail Gantt view
  • BTracking Gantt view
  • CLeveling Gantt view
  • DGantt Chart view

Unlock 74-343 to see the answer

You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 74-343 Practice