You are a project manager who uses Project Professional 2013. After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the original scheduled date

The correct answer is B. Tracking Gantt view. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Professional 2013. After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the original scheduled dates. You need a graphical view that shows the current schedule to baseline. Which view should you use?

Options

  • ADetail Gantt view
  • BTracking Gantt view
  • CLeveling Gantt view
  • DGantt Chart view

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    80% (28)
  • C
    11% (4)
  • D
    6% (2)