You are managing a project by using Project Professional 2013. Your project schedule contains 1000 tasks which are in outline format. You discover that the Design summary task is located below the…
The correct answer is D. Click on the ID number for the Design summary task grouping and drag the group above the. See the full explanation below for the reasoning.
Question
You are managing a project by using Project Professional 2013. Your project schedule contains 1000 tasks which are in outline format. You discover that the Design summary task is located below the Build summary group of tasks. You need to move the Design summary task and its detail tasks to the proper location. What should you do?
Options
- AClick on the Design summary task name and drag it above the Build group of tasks.
- BMake the Design summary task grouping a manual task, and drag the Design task name
- CCut all of the tasks below the Design summary task and paste them above the Build group of
- DClick on the ID number for the Design summary task grouping and drag the group above the
How the community answered
(39 responses)- A18% (7)
- B3% (1)
- C8% (3)
- D72% (28)