nerdexam
Microsoft

74-343 · Question #15

74-343 Question #15: Real Exam Question with Answer & Explanation

Sign in or unlock 74-343 to reveal the answer and full explanation for question #15. The question stem and answer options stay visible for context.

Question

You are a manager for an organization that uses Project Professional 2013. A critical project shows average finish variance values between 5-10 days for the tasks. You need to interpret these variance values to determine the next course of action to take. What do these variance values mean?

Options

  • AThe project is on schedule.
  • BThe project is running between 5-10 days ahead of schedule.
  • CThe project is running between 5-10 days behind schedule.
  • DThe project is averaging a normal performance timeline.

Unlock 74-343 to see the answer

You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 74-343 Practice