74-343 · Question #15
You are a manager for an organization that uses Project Professional 2013. A critical project shows average finish variance values between 5-10 days for the tasks. You need to interpret these…
The correct answer is C. The project is running between 5-10 days behind schedule. See the full explanation below for the reasoning.
Question
You are a manager for an organization that uses Project Professional 2013. A critical project shows average finish variance values between 5-10 days for the tasks. You need to interpret these variance values to determine the next course of action to take. What do these variance values mean?
Options
- AThe project is on schedule.
- BThe project is running between 5-10 days ahead of schedule.
- CThe project is running between 5-10 days behind schedule.
- DThe project is averaging a normal performance timeline.
How the community answered
(19 responses)- A5% (1)
- B16% (3)
- C74% (14)
- D5% (1)