74-343 · Question #15

You are a manager for an organization that uses Project Professional 2013. A critical project shows average finish variance values between 5-10 days for the tasks. You need to interpret these…

The correct answer is C. The project is running between 5-10 days behind schedule. See the full explanation below for the reasoning.

Question

You are a manager for an organization that uses Project Professional 2013. A critical project shows average finish variance values between 5-10 days for the tasks. You need to interpret these variance values to determine the next course of action to take. What do these variance values mean?

Options

  • AThe project is on schedule.
  • BThe project is running between 5-10 days ahead of schedule.
  • CThe project is running between 5-10 days behind schedule.
  • DThe project is averaging a normal performance timeline.

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    16% (3)
  • C
    74% (14)
  • D
    5% (1)