Question
You are a project manager who uses Project Professional 2013. When viewing the critical path, you notice that there are some inconsistencies. To investigate the status of the critical path, you insert the Total Slack column into a task table. You discover that many of the tasks have negative Total Slack values. You need to resolve the negative Total Slack values. What should you do?
Options
- ARemove lag time from task relationships.
- BRemove as many constraints as possible.
- CRe-assign resources that have more availability at the time of the negative slack.
- DRemove lead time from the task relationships.