You manage a project by using Project Professional 2013. A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in…
The correct answer is A. Click on the task, and click Inactivate. See the full explanation below for the reasoning.
Question
You manage a project by using Project Professional 2013. A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future. You need to implement a solution to meet the stakeholder's request. What should you do?
Options
- AClick on the task, and click Inactivate.
- BMove the task to after the ending date for the project.
- CDelete the task from the schedule.
- DClick the Unlink Task button to unlink the predecessors and successors for the task.
How the community answered
(31 responses)- A81% (25)
- B6% (2)
- C10% (3)
- D3% (1)