Question
You manage a project by using Project Professional 2013. The work variance for a task is 48 hours. The remaining work is 25 hours. The work for this task has been completed. You need the work variance to be adjusted to reflect what has occurred during the performance of the task. What should you do?
Options
- AAdjust the value in the Baseline Work column.
- BEnter a 0 in the remaining Duration column.
- CAdjust the value in the Work Variance column.
- DMark the task inactive.