You manage a project and use Project Professional 2013 to track your project schedule. One of several resources assigned to a fixed-unit, effort-driven, five-day task is assigned at 50% of their…

The correct answer is D. Use the Task Form formatted to show Schedule Details and add a three-day delay to the. See the full explanation below for the reasoning.

Question

You manage a project and use Project Professional 2013 to track your project schedule. One of several resources assigned to a fixed-unit, effort-driven, five-day task is assigned at 50% of their availability. The resource asks to start the task three days later than planned because of a scheduling conflict. The schedule change is approved. You need to make the adjustment to the resource assignment to accommodate this request without affecting the other resources assigned to the task. What should you do?

Options

  • AUse the Resource Usage view and add duration to the assignment to extend the deadline
  • BUse the Gantt Chart view tracking table and add a Start no earlier than constraint to the task.
  • CUse the Task Form formatted to show Work Details and add a three-day delay to the
  • DUse the Task Form formatted to show Schedule Details and add a three-day delay to the

How the community answered

(22 responses)
  • A
    18% (4)
  • B
    5% (1)
  • C
    5% (1)
  • D
    73% (16)