74-343 · Question #19
74-343 Question #19: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #19. The question stem and answer options stay visible for context.
Question
You manage a project and use Project Professional 2013 to track your project schedule. One of several resources assigned to a fixed-unit, effort-driven, five-day task is assigned at 50% of their availability. The resource asks to start the task three days later than planned because of a scheduling conflict. The schedule change is approved. You need to make the adjustment to the resource assignment to accommodate this request without affecting the other resources assigned to the task. What should you do?
Options
- AUse the Resource Usage view and add duration to the assignment to extend the deadline
- BUse the Gantt Chart view tracking table and add a Start no earlier than constraint to the task.
- CUse the Task Form formatted to show Work Details and add a three-day delay to the
- DUse the Task Form formatted to show Schedule Details and add a three-day delay to the