Question

You manage a project by using Project Standard 2013. You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2. What should you do?

Options

  • AEnter physical percent complete for the tasks that have actual values.
  • BChange the Earned Value method to Baseline2 in the Task Information Form.
  • CChange the Baseline for Earned Value calculation option to Baseline2, and reschedule
  • DGo to the Earned Value table and insert the Baseline2 column.