74-343 · Question #14

You manage a project by using Project Standard 2013. You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2. What should you do?

The correct answer is C. Change the Baseline for Earned Value calculation option to Baseline2, and reschedule. See the full explanation below for the reasoning.

Question

You manage a project by using Project Standard 2013. You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2. What should you do?

Options

  • AEnter physical percent complete for the tasks that have actual values.
  • BChange the Earned Value method to Baseline2 in the Task Information Form.
  • CChange the Baseline for Earned Value calculation option to Baseline2, and reschedule
  • DGo to the Earned Value table and insert the Baseline2 column.

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    9% (2)
  • C
    83% (19)
  • D
    4% (1)