Microsoft
74-343 · Question #14
74-343 Question #14: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #14. The question stem and answer options stay visible for context.
Question
You manage a project by using Project Standard 2013. You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2. What should you do?
Options
- AEnter physical percent complete for the tasks that have actual values.
- BChange the Earned Value method to Baseline2 in the Task Information Form.
- CChange the Baseline for Earned Value calculation option to Baseline2, and reschedule
- DGo to the Earned Value table and insert the Baseline2 column.
Unlock 74-343 to see the answer
You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.