You are a project manager who uses Project Professional 2013. You have created a project which involves three other colleagues who are also using Project Professional 2013. You and your colleagues…

The correct answer is A. Save and sync your project by using SkyDrive. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Professional 2013. You have created a project which involves three other colleagues who are also using Project Professional 2013. You and your colleagues are over budget and cannot spend any more money on this project. To ensure that the latest version of the project file is always the one being used, you need to save, share, and sync this project plan File among your colleagues without using email. What should you do?

Options

  • ASave and sync your project by using SkyDrive.
  • BSave and sync selected tasks in the project by using SkyDrive.
  • CSave and sync your project to a shared Microsoft Excel file.
  • DSave and sync selected tasks in your Microsoft SharePoint Tasks List.

How the community answered

(36 responses)
  • A
    81% (29)
  • B
    3% (1)
  • C
    11% (4)
  • D
    6% (2)

Community Discussion

No community discussion yet for this question.

Full 74-343 Practice