You are a project manager for a company that uses Project Professional 2013. You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt…
The correct answer is D. Go to the View tab and select Display AutoFilter. See the full explanation below for the reasoning.
Question
You are a project manager for a company that uses Project Professional 2013. You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt Chart view that uses the standard Entry table. You need to communicate the progress of tasks that have a finish date of either October 2 or October 22. What should you do?
Options
- AGo to the Task tab, open the Find window, and set the parameters to find the required dates,
- BGo to the View tab, open the More Views window, and create a new view.
- CGo to the View tab and use the Date Range filter.
- DGo to the View tab and select Display AutoFilter.
How the community answered
(20 responses)- A10% (2)
- B5% (1)
- C5% (1)
- D80% (16)