nerdexam
Microsoft

74-343 · Question #37

You are a project manager for a company that uses Project Professional 2013. You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt…

The correct answer is D. Go to the View tab and select Display AutoFilter. See the full explanation below for the reasoning.

Question

You are a project manager for a company that uses Project Professional 2013. You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt Chart view that uses the standard Entry table. You need to communicate the progress of tasks that have a finish date of either October 2 or October 22. What should you do?

Options

  • AGo to the Task tab, open the Find window, and set the parameters to find the required dates,
  • BGo to the View tab, open the More Views window, and create a new view.
  • CGo to the View tab and use the Date Range filter.
  • DGo to the View tab and select Display AutoFilter.

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    5% (1)
  • C
    5% (1)
  • D
    80% (16)

Community Discussion

No community discussion yet for this question.

Full 74-343 Practice