You are a project manager who uses Project Professional 2013. You have worked on a project for four years and have created a very detailed project plan in Project Professional 2013. You use…

The correct answer is D. Add all summary tasks to your timeline. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Professional 2013. You have worked on a project for four years and have created a very detailed project plan in Project Professional 2013. You use milestones as key deliverables, and you use summary tasks as phases. Your company requests a presentation of the key deliverables for each phase of your project plan in a simple and consolidated view that fits in one Microsoft PowerPoint slide. You need to ensure that phases and key deliverables are clearly shown in the timeline and are not confusing to the audience. What should you do?

Options

  • ACreate a new Timeline view from existing tasks in your project plan.
  • BCreate a new Timeline view that automatically shows milestones for each stage of your
  • CAdd all summary tasks to your timeline.
  • DAdd all summary tasks to your timeline.

How the community answered

(55 responses)
  • A
    9% (5)
  • B
    16% (9)
  • C
    4% (2)
  • D
    71% (39)