Your organization uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. As you build the task breakdown, you notice a potential scheduling…
The correct answer is C. Evaluate the task by using the Task Inspector. See the full explanation below for the reasoning.
Question
Your organization uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. As you build the task breakdown, you notice a potential scheduling problem indicated by a wavy red line under the finish date of a detail task. You need to determine the cause of the wavy red line. What should you do?
Options
- AEvaluate the task to determine if there is a deadline.
- BInsert the Constraint Type field and view the task constraints.
- CEvaluate the task by using the Task Inspector.
- DView the Resource Sheet to see if you have overallocated resources.
How the community answered
(51 responses)- A4% (2)
- B2% (1)
- C84% (43)
- D10% (5)