Your company uses Project Professional 2013. You have two projects, Project 1 and Project 2, as well as a resource pool to contain all of the resources. You use resource leveling and want to…

The correct answer is D. Set Project Priority higher for Project 1, and then set resource leveling to level by priority. See the full explanation below for the reasoning.

Question

Your company uses Project Professional 2013. You have two projects, Project 1 and Project 2, as well as a resource pool to contain all of the resources. You use resource leveling and want to prioritize the projects so that Project 1 is the highest priority project and gets all the required resource availability first. Project 2 then gets resources as they become available from Project 1. You need to maintain this priority throughout the execution of the project. What should you do?

Options

  • ASet resource leveling to prioritize by project, priority, and standard.
  • BMake sure the resource pool is configured to list Project 1 first.
  • CLevel Project 1 first, and then level Project 2.
  • DSet Project Priority higher for Project 1, and then set resource leveling to level by priority,

How the community answered

(37 responses)
  • A
    8% (3)
  • B
    16% (6)
  • C
    5% (2)
  • D
    70% (26)

Community Discussion