Question

Your company uses Project Professional 2013. You have two projects, Project 1 and Project 2, as well as a resource pool to contain all of the resources. You use resource leveling and want to prioritize the projects so that Project 1 is the highest priority project and gets all the required resource availability first. Project 2 then gets resources as they become available from Project 1. You need to maintain this priority throughout the execution of the project. What should you do?

Options

  • ASet resource leveling to prioritize by project, priority, and standard.
  • BMake sure the resource pool is configured to list Project 1 first.
  • CLevel Project 1 first, and then level Project 2.
  • DSet Project Priority higher for Project 1, and then set resource leveling to level by priority,