You are using Project Standard 2013. Management wants to see an overview of your project that shows the overall start and finish dates, total duration, and the name of the project. They want to see…
The correct answer is D. On the format ribbon, check the box next to Summary Tasks. See the full explanation below for the reasoning.
Question
You are using Project Standard 2013. Management wants to see an overview of your project that shows the overall start and finish dates, total duration, and the name of the project. They want to see this information in a simple layout that does not include task details. You need to show one line item that displays all the requested information in the Gantt view. What should you do?
Options
- AApply the Top Level Tasks filter.
- BOn the format ribbon, check the box next to Project Summary Task.
- CApply the default Summary Tasks filter.
- DOn the format ribbon, check the box next to Summary Tasks.
How the community answered
(49 responses)- A4% (2)
- B4% (2)
- C12% (6)
- D80% (39)