nerdexam
Microsoft

74-343 · Question #30

You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. You create two manually scheduled tasks and…

The correct answer is D. Select the successor task and click Respect Links. See the full explanation below for the reasoning.

Question

You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. You create two manually scheduled tasks and link them in a Finish to Start relationship. The project team member asks you to increase the duration of the predecessor task. You notice that the successor task start date is now before the finish date of the predecessor task. You want the successor task to start after the predecessor finishes. What should you do?

Options

  • ASelect both tasks and click Unlink.
  • BSelect the successor task and click Mark on Track.
  • CSelect the predecessor task and click Respect Links.
  • DSelect the successor task and click Respect Links.

How the community answered

(39 responses)
  • A
    10% (4)
  • B
    3% (1)
  • C
    5% (2)
  • D
    82% (32)

Community Discussion

No community discussion yet for this question.

Full 74-343 Practice