74-343 · Question #35
You are a project manager who uses Project Standard 2013. You work on a project that requires you to generate many documents. Each task in your project plan must have a document associated and stored
The correct answer is E. Copy the SharePoint URL of each document and paste in the Hyperlink task standard field. See the full explanation below for the reasoning.
Question
You are a project manager who uses Project Standard 2013. You work on a project that requires you to generate many documents. Each task in your project plan must have a document associated and stored in your Microsoft SharePoint Intranet Environment. These documents are 25 megabytes in size. You need to share this project plan by email with your team and ensure that they can easily access the documents. What should you do?
Options
- AIn the Task Information notes, insert an object from a file.
- BCreate a task custom field named Link to Document, and select the field type as Text
- CCopy and paste the document into your Gantt chart, and create a link between your task and
- DGo to backstage and use the feature Add and Link a SharePoint Document to My Tasks to
- ECopy the SharePoint URL of each document and paste in the Hyperlink task standard field
How the community answered
(34 responses)- A3% (1)
- B3% (1)
- C6% (2)
- D12% (4)
- E76% (26)