Microsoft
74-343 · Question #9
74-343 Question #9: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #9. The question stem and answer options stay visible for context.
Question
You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to update your project to reflect your organization's scheduled two- week closure. You need to reflect the closure within your schedule. What should you do?
Options
- ACreate a resource and specify non-working days for the resource which reflect the closure.
- BOpen the Project Calendar and modify the default work week by setting the dates as
- CCreate a new calendar and assign this to the tasks that are scheduled over the period of
- DOpen the Project Calendar and enter the planned closure in the Exceptions tab.
Unlock 74-343 to see the answer
You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.