74-343 · Question #9

You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to update your project to reflect your organization's scheduled two- week closure. You need to reflect the…

The correct answer is D. Open the Project Calendar and enter the planned closure in the Exceptions tab. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to update your project to reflect your organization's scheduled two- week closure. You need to reflect the closure within your schedule. What should you do?

Options

  • ACreate a resource and specify non-working days for the resource which reflect the closure.
  • BOpen the Project Calendar and modify the default work week by setting the dates as
  • CCreate a new calendar and assign this to the tasks that are scheduled over the period of
  • DOpen the Project Calendar and enter the planned closure in the Exceptions tab.

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    13% (4)
  • C
    6% (2)
  • D
    78% (25)

Community Discussion

No community discussion yet for this question.