Question
You are a project manager who uses Project Standard 2013. Your manager wants you to plan an office move. You have a project schedule from a prior office move named "OfficeMove.mpp" and you want to use this project to assist in planning the current office move. In the fewest steps possible, you need to create your new project schedule based on the old project schedule. What should you do?
Options
- AOpen the old OfficeMove.mpp file, change the project start date and project title, and clear
- BOpen the old OfficeMove.mpp file, click on Save As, save the file using a new file name,
- COpen the old OfficeMove.mpp file, save the file as an .mpt file type, removing the baseline
- DOpen the old OfficeMove.mpp file, click on Save As, and save the file using a new file name.