You are a Project Manager who uses Project Professional 2013. You manage a critical project, which is synchronized with a Microsoft SharePoint Task List. One of your team members has changed a task…

The correct answer is B. Map the Priority field from SharePoint to Project by using File, Info. See the full explanation below for the reasoning.

Question

You are a Project Manager who uses Project Professional 2013. You manage a critical project, which is synchronized with a Microsoft SharePoint Task List. One of your team members has changed a task priority to High in SharePoint, and you do not see the changed data in Project Professional 2013. What should you do?

Options

  • AUse the Organizer to copy the Priority field from the SharePoint Task List.
  • BMap the Priority field from SharePoint to Project by using File, Info.
  • CMap the Priority field from SharePoint to Project by using Project, Custom Fields, Import Field.
  • DUse the Task Information box to copy the Priority field from the SharePoint Task List.

How the community answered

(17 responses)
  • B
    82% (14)
  • C
    12% (2)
  • D
    6% (1)