You are a Project Manager who uses Project Professional 2013. You manage a critical project, which is synchronized with a Microsoft SharePoint Task List. One of your team members has changed a task…
The correct answer is B. Map the Priority field from SharePoint to Project by using File, Info. See the full explanation below for the reasoning.
Question
You are a Project Manager who uses Project Professional 2013. You manage a critical project, which is synchronized with a Microsoft SharePoint Task List. One of your team members has changed a task priority to High in SharePoint, and you do not see the changed data in Project Professional 2013. What should you do?
Options
- AUse the Organizer to copy the Priority field from the SharePoint Task List.
- BMap the Priority field from SharePoint to Project by using File, Info.
- CMap the Priority field from SharePoint to Project by using Project, Custom Fields, Import Field.
- DUse the Task Information box to copy the Priority field from the SharePoint Task List.
How the community answered
(17 responses)- B82% (14)
- C12% (2)
- D6% (1)
Community Discussion