74-343 · Question #49
74-343 Question #49: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #49. The question stem and answer options stay visible for context.
Question
You are a project manager who uses Microsoft Excel 2013. Your company decides to migrate all of the current projects in Microsoft Excel 2013 to Project Professional 2013. They allow all employees to spend 8 hours migrating each project plan. Your current and unique project plan has 462 tasks with duration in days, and resources have been assigned and named. You have a status meeting in two days. You need to provide your project's information by using Project Professional 2013. What should you do?
Options
- ACreate a new project plan in Project Professional 2013 and use the Gantt Chart Wizard to
- BRename the Excel file from .xlsx to .mpx, and open it by using Project Professional 2013,
- COpen the Excel File .xlsx directly from Project Professional 2013, which will convert and map
- DCreate a VBA macro by using the Excel Record Macro feature to import all tasks, durations,