Microsoft
74-343 · Question #11
You are a project manager, and your organization uses Project Standard 2013. You have created a non-working day in a resource's calendar; however, the HR department notifies you that the resource…
The correct answer is C. Open the resource's working calendar and delete the exception. See the full explanation below for the reasoning.
Question
You are a project manager, and your organization uses Project Standard 2013. You have created a non-working day in a resource's calendar; however, the HR department notifies you that the resource will work that day after all. You need to reflect this change in the project in the most efficient manner. What should you do?
Options
- AOpen the Project calendar and mark the work day as working.
- BOpen the resource's working calendar and edit the Work Week details to set the day as
- COpen the resource's working calendar and delete the exception.
- DOpen the resource's working calendar and mark the day as working.
How the community answered
(50 responses)- A8% (4)
- B18% (9)
- C70% (35)
- D4% (2)