- Question #51Predictive, Plan-Based Methodologies
A project manager needs to request outside support for a statement of work (SOW) that is not precise. Which kind of contract does the project manager need to create?
Contract typesProcurement managementStatement of Work (SOW)Time and material (T&M) - Question #52Project Management Fundamentals and Core Concepts
Which is a list of organizational systems that may have an impact on a project?
Organizational SystemsProject EnvironmentOrganizational InfluencesGovernance - Question #53Predictive, Plan-Based Methodologies
Which set of activities should a project manager use as part of the Develop Team process?
Develop TeamProject Team ManagementConflict ManagementTeam Performance - Question #54Project Management Fundamentals and Core Concepts
Which set of competencies should a project manager have?
Project Manager CompetenciesPMI Talent TriangleLeadership SkillsBusiness Acumen - Question #55Project Management Fundamentals and Core Concepts
A project it just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
Stakeholder ManagementProject ObjectivesProject SuccessStakeholder Engagement - Question #56Predictive, Plan-Based Methodologies
Which of the following set of elements is part of an effective communications management plan?
Communications Management PlanProject CommunicationsProject PlanningPlan Components - Question #57Predictive, Plan-Based Methodologies
Which is the order of steps in the Procurement Management process?
Procurement ManagementProcess OrderPMBOK Processes - Question #58Predictive, Plan-Based Methodologies
Which is the appropriate tool to identify the possible correlation between two elements in a process?
Quality Management ToolsData AnalysisCorrelationScatter Diagram - Question #59Predictive, Plan-Based Methodologies
What process is included in Project Integration Management?
Project Integration ManagementProject Management ProcessesMonitoring and Controlling - Question #60Predictive, Plan-Based Methodologies
What are the inputs of the Estimate Costs process?
Estimate CostsCost ManagementInputsProject Management Process - Question #61Project Management Fundamentals and Core Concepts
In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?
Organizational structuresMatrix organizationProject manager authorityResource allocation - Question #62Predictive, Plan-Based Methodologies
The project manager implemented the stakeholder engagement plan and realized that some updates should be made. Which components of the project management plan should be modified?
Stakeholder EngagementCommunications ManagementProject Plan Updates - Question #63Predictive, Plan-Based Methodologies
In which Project Cost Management process is work performance data included?
Project Cost ManagementControl CostsWork Performance DataPMBOK Processes - Question #64Agile Frameworks/Methodologies
In a project using agile methodology, who may perform the quality control activities?
Agile Quality ControlTeam ResponsibilitiesAgile Principles - Question #65Project Management Fundamentals and Core Concepts
What does earned value (EV) measure?
Earned Value (EV)Earned Value Management (EVM)Project Performance MeasurementCost Management - Question #66Predictive, Plan-Based Methodologies
How can a project manager represent a contingency reserve in the schedule?
Contingency ReserveSchedule ManagementRisk ManagementProject Planning - Question #67Agile Frameworks/Methodologies
A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager's key responsibility during this phase?
Agile Project ManagementPM Role (Agile)CollaborationProject Integration Management - Question #68Predictive, Plan-Based Methodologies
Which statement describes the relationship between Manage Quality process and Control Quality process?
Project Quality ManagementManage QualityControl Quality - Question #69Predictive, Plan-Based Methodologies
At what stages of a project should the Identify Stakeholders process be performed?
Identify StakeholdersStakeholder ManagementProject LifecycleProcess Timing - Question #70Predictive, Plan-Based Methodologies
curious about the difference between a verified deliverable and an accepted deliverable. Which of the following definitions can the project manager use to explain the difference?
Verified DeliverablesAccepted DeliverablesControl Quality ProcessValidate Scope Process - Question #71Agile Frameworks/Methodologies
Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?
Self-organizing teamsAgile team managementTeam collaborationDynamic project environments - Question #72Project Management Fundamentals and Core Concepts
How is the Project Scope Management process different in agile and adaptive projects than in traditional projects?
Scope ManagementAgile ProjectsAdaptive ProjectsPredictive Projects - Question #73Predictive, Plan-Based Methodologies
What is the purpose of the project management process groups?
Project Management Process GroupsPMBOK GuideProject LifecyclePredictive Methodology - Question #74Predictive, Plan-Based Methodologies
After an internal deliverable review session with the team, the project manager identifies some issues that need to be fixed before submitting the deliverable for formal approval....
Quality ManagementCost of QualityAppraisal CostsRework - Question #75Predictive, Plan-Based Methodologies
During which process of Project Cost Management does a project manager produce the cost baseline?
Project Cost ManagementCost BaselineDetermine BudgetPMBOK Processes - Question #76Project Management Fundamentals and Core Concepts
Company A's accountant sends notification about a change in the company's tax classification. Why would a project have to be initiated?
Project initiationBusiness driversRegulatory complianceProject triggers - Question #77Predictive, Plan-Based Methodologies
The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?
Project Resource ManagementDevelop TeamCo-locationTraining - Question #78Agile Frameworks/Methodologies
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
Agile Stakeholder EngagementAdaptive Scope ManagementCustomer InvolvementContinuous Engagement - Question #79Project Management Fundamentals and Core Concepts
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which...
Communication methodsPull communicationLessons learned databaseInformation management - Question #80Predictive, Plan-Based Methodologies
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the infor...
Communications ManagementStakeholder EngagementProject PlanningStatus Reporting - Question #81Project Management Fundamentals and Core Concepts
The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?
Project Manager SkillsStrategic ManagementBusiness AcumenPMI Talent Triangle - Question #82Predictive, Plan-Based Methodologies
What tool should a project manager use to efficiently manage project resources?
Resource ManagementResource Breakdown Structure (RBS)Project Planning - Question #83Predictive, Plan-Based Methodologies
Which process is engaged when a project team member makes a change to project budget with the project manager's approval?
Project Cost ManagementControl CostsBudget ManagementChange Management - Question #84Project Management Fundamentals and Core Concepts
Which conflict resolution technique produces the most lasting results?
Conflict ResolutionTeam ManagementCommunicationProblem Solving - Question #85Predictive, Plan-Based Methodologies
What is the best tool to calculate the critical path on a project?
Critical Path Method (CPM)Project Network DiagramSchedule ManagementProject Planning - Question #86Predictive, Plan-Based Methodologies
In which of the Risk Management processes is the project charter used as an input?
Risk ManagementProject CharterPMI ProcessesProcess Inputs - Question #87Project Management Fundamentals and Core Concepts
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?
Portfolio ManagementOrganizational Project ManagementStrategic AlignmentPMI Terminology - Question #88Project Management Fundamentals and Core Concepts
What is the discipline that focuses on the interdependencies between projects to determine the optimal approach for managing them?
Program ManagementProject RelationshipsOrganizational Project Management - Question #89Project Management Fundamentals and Core Concepts
A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterat...
TailoringProject Life CycleAdaptive ApproachesProject Dimensions - Question #90Project Management Fundamentals and Core Concepts
A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?
Project CommunicationCommunication MethodsDelegation - Question #91Predictive, Plan-Based Methodologies
Creating the project scope statement is part of which process?
Scope ManagementDefine Scope ProcessProject Scope StatementProject Planning - Question #92Predictive, Plan-Based Methodologies
What organizational asset can influence the Plan Risk Management process?
Organizational Process Assets (OPAs)Plan Risk ManagementStakeholder ManagementProject Planning Inputs - Question #93Predictive, Plan-Based Methodologies
A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Eac...
DecompositionEffort EstimationScope DefinitionWork Breakdown Structure - Question #94Predictive, Plan-Based Methodologies
Due to new market conditions a five-year project requires a full revision of project objectives. Which components of the stakeholder engagement plan need to be updated?
Stakeholder ManagementChange ManagementProject ObjectivesProject Scope - Question #95Project Management Fundamentals and Core Concepts
The project team is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive,...
Project Life CycleAdaptive ApproachesHybrid ApproachesMethodology Selection - Question #96Adaptive Frameworks/Methodologies
A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement management does this project require?
Stakeholder EngagementProject ChangeAdaptive PrinciplesCommunication Management - Question #97Predictive, Plan-Based Methodologies
A project manager is identifying the risks of a project. Which technique should the project manager use?
Risk ManagementRisk IdentificationPrompt ListsTools and Techniques - Question #98Predictive, Plan-Based Methodologies
The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project mana...
Communications ManagementManage Communications ProcessInformation DistributionProject Information Flow - Question #99Agile Frameworks/Methodologies
The Agile principle "welcome changing requirements, even late in development" relates to which agile manifesto?
Agile ManifestoAgile principlesResponding to change - Question #100Project Management Fundamentals and Core Concepts
Which of the following best correspond to the organizational process assets (OPAs) that affect the project?
Organizational Process Assets (OPAs)Project EnvironmentProject Management Fundamentals