nerdexam
PMI

CAPM · Question #77

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

The correct answer is D. Develop Team. Co-location (also called a 'war room' - placing team members in the same physical location) and training are both recognized tools and techniques of the Develop Team process in Project Resource Management. Develop Team focuses on improving team competencies, interaction, and…

Predictive, Plan-Based Methodologies

Question

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Options

  • AAcquire Resources
  • BControl Resources
  • CManage Team
  • DDevelop Team

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    16% (4)
  • C
    4% (1)
  • D
    76% (19)

Explanation

Co-location (also called a 'war room' - placing team members in the same physical location) and training are both recognized tools and techniques of the Develop Team process in Project Resource Management. Develop Team focuses on improving team competencies, interaction, and overall team environment to enhance project performance. Option A (Acquire Resources) is about obtaining the human and physical resources needed. Option B (Control Resources) is about ensuring resources are available as planned and monitoring their usage. Option C (Manage Team) focuses on tracking performance, providing feedback, resolving conflicts, and managing team changes - not on building skills or improving cohesion through co-location and training.

Topics

#Project Resource Management#Develop Team#Co-location#Training

Community Discussion

No community discussion yet for this question.

Full CAPM Practice