CAPM · Question #77
The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?
The correct answer is D. Develop Team. Co-location (also called a 'war room' - placing team members in the same physical location) and training are both recognized tools and techniques of the Develop Team process in Project Resource Management. Develop Team focuses on improving team competencies, interaction, and…
Question
Options
- AAcquire Resources
- BControl Resources
- CManage Team
- DDevelop Team
How the community answered
(25 responses)- A4% (1)
- B16% (4)
- C4% (1)
- D76% (19)
Explanation
Co-location (also called a 'war room' - placing team members in the same physical location) and training are both recognized tools and techniques of the Develop Team process in Project Resource Management. Develop Team focuses on improving team competencies, interaction, and overall team environment to enhance project performance. Option A (Acquire Resources) is about obtaining the human and physical resources needed. Option B (Control Resources) is about ensuring resources are available as planned and monitoring their usage. Option C (Manage Team) focuses on tracking performance, providing feedback, resolving conflicts, and managing team changes - not on building skills or improving cohesion through co-location and training.
Topics
Community Discussion