CAPM · Question #101
What is a tailoring consideration in Project Integration Management?
The correct answer is B. Benefits. This question tests knowledge of tailoring considerations specific to Project Integration Management, where benefits realization is a key dimension that must be adapted per project context.
Question
Options
- AValidation and control
- BBenefits
- CTechnology support
- DPhysical location
How the community answered
(34 responses)- A3% (1)
- B91% (31)
- D6% (2)
Why each option
This question tests knowledge of tailoring considerations specific to Project Integration Management, where benefits realization is a key dimension that must be adapted per project context.
Validation and control describes process activities within the Monitoring and Controlling process group, not a tailoring consideration unique to Project Integration Management.
Benefits is a recognized tailoring consideration for Project Integration Management because organizations must determine how benefits will be identified, tracked, and managed throughout the project lifecycle. The approach to benefits realization varies based on organizational complexity, governance structures, and project scope, requiring deliberate tailoring decisions by the project manager.
Technology support is not a tailoring consideration for Project Integration Management; it is more relevant to resource, communications, or procurement management decisions.
Physical location is a tailoring consideration associated with Project Resource Management or Communications Management, reflecting where team members are located, not Integration Management.
Concept tested: Tailoring considerations in Project Integration Management
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics