Which of the following lists represents the outputs of the Monitor Communications process?

The correct answer is B. Work performance information, change requests, project management plan updates, and project documents updates. According to the PMBOK Guide, the Monitor Communications process produces the following outputs: Work Performance Information, Change Requests, Project Management Plan Updates, Project Documents Updates, and Organizational Process Assets Updates. Option B correctly identifies the

Predictive, Plan-Based Methodologies

Question

Which of the following lists represents the outputs of the Monitor Communications process?

Options

  • AProject communications, project management plan updates, project documents updates, and organizational process assets updates
  • BWork performance information, change requests, project management plan updates, and project documents updates
  • CCommunications management plan, project management plan updates, work performance report, and project documents update
  • DStakeholder engagement plan, change requests, project management plan updates, and project documents updates

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    90% (18)
  • C
    5% (1)

Explanation

According to the PMBOK Guide, the Monitor Communications process produces the following outputs: Work Performance Information, Change Requests, Project Management Plan Updates, Project Documents Updates, and Organizational Process Assets Updates. Option B correctly identifies the core outputs. Option A incorrectly includes 'Project Communications,' which is an output of the Manage Communications process, not Monitor Communications. Option C incorrectly lists the 'Communications Management Plan' and 'Work Performance Report' as outputs; the communications management plan is an output of Plan Communications Management. Option D incorrectly includes the 'Stakeholder Engagement Plan,' which belongs to the Plan Stakeholder Engagement process.