The correct answer is B: Work performance information, change requests, project management plan updates, and project documents updates. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which of the following lists represents the outputs of the Monitor Communications process?
Options
- AProject communications, project management plan updates, project documents updates, and organizational process assets updates
- BWork performance information, change requests, project management plan updates, and project documents updates
- CCommunications management plan, project management plan updates, work performance report, and project documents update
- DStakeholder engagement plan, change requests, project management plan updates, and project documents updates
Topics
#Monitor Communications#Process Outputs#Communications Management#PMI Processes