CAPM · Question #227

CAPM Question #227: Real Exam Question with Answer & Explanation

The correct answer is B: Work performance information, change requests, project management plan updates, and project documents updates. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which of the following lists represents the outputs of the Monitor Communications process?

Options

  • AProject communications, project management plan updates, project documents updates, and organizational process assets updates
  • BWork performance information, change requests, project management plan updates, and project documents updates
  • CCommunications management plan, project management plan updates, work performance report, and project documents update
  • DStakeholder engagement plan, change requests, project management plan updates, and project documents updates

Topics

#Monitor Communications#Process Outputs#Communications Management#PMI Processes