PMIPMI
CAPM · Question #226
CAPM Question #226: Real Exam Question with Answer & Explanation
The correct answer is A: Use a lightweight cost estimation due to the nature of agile projects. See the full explanation below for the reasoning.
Agile Frameworks/Methodologies
Question
In a preliminary meeting for a project, team members decide to execute the project with agile methodology. A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?
Options
- AUse a lightweight cost estimation due to the nature of agile projects
- BUse a detailed cost estimation for agile projects
- CRetrieve a budget from a previous project and create a baseline for this project based on it
- DUse a detailed work breakdown structure (WBS) to get cost estimation
Topics
#Agile cost estimation#Lightweight estimation#Agile planning#Progressive elaboration
Community Discussion
No community discussion yet for this question.