nerdexam
PMIPMI

CAPM · Question #226

CAPM Question #226: Real Exam Question with Answer & Explanation

The correct answer is A: Use a lightweight cost estimation due to the nature of agile projects. See the full explanation below for the reasoning.

Agile Frameworks/Methodologies

Question

In a preliminary meeting for a project, team members decide to execute the project with agile methodology. A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

Options

  • AUse a lightweight cost estimation due to the nature of agile projects
  • BUse a detailed cost estimation for agile projects
  • CRetrieve a budget from a previous project and create a baseline for this project based on it
  • DUse a detailed work breakdown structure (WBS) to get cost estimation

Topics

#Agile cost estimation#Lightweight estimation#Agile planning#Progressive elaboration

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions