nerdexam
PMI

CAPM · Question #435

What is the Project Schedule Management practice used to deliver incremental value to the customer?

The correct answer is B. Iterative scheduling with a backlog. Iterative scheduling with a backlog is the Project Schedule Management technique specifically designed to deliver incremental value to the customer. In agile frameworks, work items are maintained in a prioritized backlog and pulled into time-boxed iterations (sprints), with worki

Agile Frameworks/Methodologies

Question

What is the Project Schedule Management practice used to deliver incremental value to the customer?

Options

  • AResource optimization
  • BIterative scheduling with a backlog
  • COn-demand scheduling
  • DCritical path method

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    90% (35)
  • C
    3% (1)
  • D
    5% (2)

Explanation

Iterative scheduling with a backlog is the Project Schedule Management technique specifically designed to deliver incremental value to the customer. In agile frameworks, work items are maintained in a prioritized backlog and pulled into time-boxed iterations (sprints), with working deliverables produced at the end of each iteration. This enables continuous feedback and incremental value delivery. On-demand scheduling (C) is used in Kanban-style systems for flow-based work. Resource optimization (A) and the Critical Path Method (D) are deterministic scheduling techniques that do not inherently focus on incremental delivery to the customer.

Topics

#Agile Scheduling#Iterative Planning#Backlog Management#Incremental Delivery

Community Discussion

No community discussion yet for this question.

Full CAPM Practice