CAPM Question #436: Real Exam Question with Answer & Explanation

The correct answer is B: Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What benefit does the Manage Stakeholder Engagement process offer?

Options

  • AAllows the project manager to increase support and minimize resistance from stakeholders
  • BMaintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes
  • CProvides an actionable plan to interact effectively with stakeholders
  • DEnables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders

Topics

#Stakeholder Management#Manage Stakeholder Engagement#Project Execution#PMBOK Processes

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions