CAPM · Question #267
If you established a contingency reserve including time, money, and resources, how are you handling risk?
The correct answer is A. Accepting. Establishing a contingency reserve (time, money, and resources) is a form of active risk acceptance. Risk acceptance means the project team acknowledges the risk exists but chooses not to change the plan to deal with it proactively - instead, they set aside reserves to handle…
Question
Options
- AAccepting
- BTransferring
- CAvoiding
- DMitigating
How the community answered
(24 responses)- A92% (22)
- B4% (1)
- D4% (1)
Explanation
Establishing a contingency reserve (time, money, and resources) is a form of active risk acceptance. Risk acceptance means the project team acknowledges the risk exists but chooses not to change the plan to deal with it proactively - instead, they set aside reserves to handle it if it occurs. This contrasts with: avoiding (changing the plan to eliminate the risk entirely), mitigating (reducing the probability or impact), and transferring (shifting the financial impact to a third party, such as via insurance or contract). Contingency reserves are the hallmark of active acceptance, not mitigation.
Topics
Community Discussion
No community discussion yet for this question.