nerdexam
PMIPMI

CAPM · Question #268

CAPM Question #268: Real Exam Question with Answer & Explanation

The correct answer is C: Enterprise environmental factors, organizational process assets, project charter, and project management plan. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which are required to create the schedule management plan?

Options

  • AScope baseline, work breakdown structure (WBS), estimated costs, and milestone list
  • BResource management plan, organizational process assets, activity list, and business case
  • CEnterprise environmental factors, organizational process assets, project charter, and project management plan
  • DActivity list, project statement of work, project charter, and communications management plan

Topics

#Schedule Management#PMBOK Inputs#Planning Process Group#Project Management Plan

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions