CAPM · Question #268
Which are required to create the schedule management plan?
The correct answer is C. Enterprise environmental factors, organizational process assets, project charter, and project management plan. The Plan Schedule Management process has four key inputs per the PMBOK Guide: the Project Charter (provides high-level milestones and summary schedule), the Project Management Plan (including scope management plan and development approach), Enterprise Environmental Factors…
Question
Options
- AScope baseline, work breakdown structure (WBS), estimated costs, and milestone list
- BResource management plan, organizational process assets, activity list, and business case
- CEnterprise environmental factors, organizational process assets, project charter, and project management plan
- DActivity list, project statement of work, project charter, and communications management plan
How the community answered
(34 responses)- A3% (1)
- B6% (2)
- C91% (31)
Explanation
The Plan Schedule Management process has four key inputs per the PMBOK Guide: the Project Charter (provides high-level milestones and summary schedule), the Project Management Plan (including scope management plan and development approach), Enterprise Environmental Factors (EEFs, such as scheduling tools, organizational culture, resource availability), and Organizational Process Assets (OPAs, such as historical schedule data and templates). The other answer choices mix in outputs from other processes (e.g., the activity list is an output of Define Activities, not an input to Plan Schedule Management) or unrelated documents (e.g., business case, statement of work).
Topics
Community Discussion