CAPM · Question #268
CAPM Question #268: Real Exam Question with Answer & Explanation
The correct answer is C: Enterprise environmental factors, organizational process assets, project charter, and project management plan. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which are required to create the schedule management plan?
Options
- AScope baseline, work breakdown structure (WBS), estimated costs, and milestone list
- BResource management plan, organizational process assets, activity list, and business case
- CEnterprise environmental factors, organizational process assets, project charter, and project management plan
- DActivity list, project statement of work, project charter, and communications management plan
Topics
#Schedule Management#PMBOK Inputs#Planning Process Group#Project Management Plan