CAPM · Question #80

CAPM Question #80: Real Exam Question with Answer & Explanation

The correct answer is C: Communications management plan. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs to make this decision?

Options

  • AOrganizational process assets
  • BChange management plan
  • CCommunications management plan
  • DResource management plan

Topics

#Communications Management#Stakeholder Engagement#Project Planning#Status Reporting