nerdexam
PMI

CAPM · Question #83

Which process is engaged when a project team member makes a change to project budget with the project manager's approval?

The correct answer is D. Control Costs. When an approved change is made to the project budget, the Control Costs process is engaged because it governs monitoring expenditures and managing changes to the cost baseline.

Predictive, Plan-Based Methodologies

Question

Which process is engaged when a project team member makes a change to project budget with the project manager's approval?

Options

  • AManage Cost Plan
  • BEstimate Costs
  • CDetermine Budget
  • DControl Costs

How the community answered

(16 responses)
  • A
    13% (2)
  • C
    6% (1)
  • D
    81% (13)

Why each option

When an approved change is made to the project budget, the Control Costs process is engaged because it governs monitoring expenditures and managing changes to the cost baseline.

AManage Cost Plan

'Manage Cost Plan' is not a recognized PMBOK process name - cost planning is handled by Plan Cost Management, which establishes policies and procedures for managing costs.

BEstimate Costs

Estimate Costs is a planning process focused on approximating monetary resources needed for project activities - it does not handle changes to an existing budget.

CDetermine Budget

Determine Budget is a planning process that aggregates estimated costs to establish the authorized cost baseline - it does not manage changes after the baseline is set.

DControl CostsCorrect

Control Costs is the monitoring and controlling process responsible for tracking project spending, identifying variances from the cost baseline, and managing approved changes to that baseline. When a team member modifies the budget with the project manager's approval, this represents an authorized cost baseline change - precisely what Control Costs manages. It uses tools like Earned Value Management and variance analysis to maintain cost performance and process change requests through integrated change control.

Concept tested: Control Costs process and cost baseline change management

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Project Cost Management#Control Costs#Budget Management#Change Management

Community Discussion

No community discussion yet for this question.

Full CAPM Practice