nerdexam
PMIPMI

CAPM · Question #83

CAPM Question #83: Real Exam Question with Answer & Explanation

The correct answer is D: Control Costs. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which process is engaged when a project team member makes a change to project budget with the project manager's approval?

Options

  • AManage Cost Plan
  • BEstimate Costs
  • CDetermine Budget
  • DControl Costs

Topics

#Project Cost Management#Control Costs#Budget Management#Change Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions