PMIPMI
CAPM · Question #83
CAPM Question #83: Real Exam Question with Answer & Explanation
The correct answer is D: Control Costs. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which process is engaged when a project team member makes a change to project budget with the project manager's approval?
Options
- AManage Cost Plan
- BEstimate Costs
- CDetermine Budget
- DControl Costs
Topics
#Project Cost Management#Control Costs#Budget Management#Change Management
Community Discussion
No community discussion yet for this question.