PMIPMI
CAPM · Question #153
CAPM Question #153: Real Exam Question with Answer & Explanation
The correct answer is B: Estimate Activity Resources. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?
Options
- APlan Resource Management
- BEstimate Activity Resources
- CEstimate Costs
- DAcquire Resources
Topics
#Project Resource Management#Estimate Activity Resources#Parametric Estimation#PMBOK Processes
Community Discussion
No community discussion yet for this question.