nerdexam
PMIPMI

CAPM · Question #153

CAPM Question #153: Real Exam Question with Answer & Explanation

The correct answer is B: Estimate Activity Resources. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

Options

  • APlan Resource Management
  • BEstimate Activity Resources
  • CEstimate Costs
  • DAcquire Resources

Topics

#Project Resource Management#Estimate Activity Resources#Parametric Estimation#PMBOK Processes

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions