A project manager held a meeting and listed all the team members' ideas for improving the product on a white board. What data gathering technique did the project manager apply?
Sign in or unlock CAPM to reveal the answer and full explanation for question #154. The question stem and answer options stay visible for context.
Project Management Fundamentals and Core Concepts
Question
A project manager held a meeting and listed all the team members' ideas for improving the product on a white board. What data gathering technique did the project manager apply?
Options
- AFocus groups
- BInterviews
- CBrainstorming
- DDelphi technique
Unlock CAPM to see the answer
You've previewed enough free CAPM questions. Unlock CAPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Data gathering techniques#Brainstorming#Project planning