nerdexam
PMIPMI

CAPM · Question #509

CAPM Question #509: Real Exam Question with Answer & Explanation

The correct answer is A: Project sponsor, business analyst, and key stakeholders. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

Who identifies project requirements in the early phase of the project?

Options

  • AProject sponsor, business analyst, and key stakeholders
  • BProject manager, business analyst, and key stakeholders
  • CBusiness analyst, product team, and key stakeholders
  • DProject manager, business analyst, and project sponsor

Topics

#Requirements elicitation#Project roles#Stakeholder management#Project initiation

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions