PMIPMI
CAPM · Question #509
CAPM Question #509: Real Exam Question with Answer & Explanation
The correct answer is A: Project sponsor, business analyst, and key stakeholders. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
Who identifies project requirements in the early phase of the project?
Options
- AProject sponsor, business analyst, and key stakeholders
- BProject manager, business analyst, and key stakeholders
- CBusiness analyst, product team, and key stakeholders
- DProject manager, business analyst, and project sponsor
Topics
#Requirements elicitation#Project roles#Stakeholder management#Project initiation
Community Discussion
No community discussion yet for this question.