CAPM · Question #510

CAPM Question #510: Real Exam Question with Answer & Explanation

The correct answer is A: Responsible, accountable, consult, inform (RACI) matrix. See the full explanation below for the reasoning.

Business Analysis Frameworks

Question

Which two of the following can be used as communication tools between the business analyst and the rest of the project team? (Choose two.)

Options

  • AResponsible, accountable, consult, inform (RACI) matrix
  • BGantt chart
  • CPareto chart
  • DProcess flows
  • EProject management plan

Topics

#Communication Tools#Business Analyst Role#RACI Matrix#Process Flows

Community Discussion

No community discussion yet for this question.