Which of the following artifacts is the business analyst's main responsibility?

The correct answer is A. Product scope. The business analyst is primarily responsible for defining and managing product scope - the features and functions that characterize the product or service being delivered.

Business Analysis Frameworks

Question

Which of the following artifacts is the business analyst's main responsibility?

Options

  • AProduct scope
  • BProject scope
  • CProject charter
  • DBusiness case

How the community answered

(29 responses)
  • A
    90% (26)
  • B
    3% (1)
  • C
    3% (1)
  • D
    3% (1)

Why each option

The business analyst is primarily responsible for defining and managing product scope - the features and functions that characterize the product or service being delivered.

AProduct scopeCorrect

Product scope defines the features, functions, and behaviors of the deliverable itself, and the business analyst is the key owner of this artifact, eliciting and documenting requirements that shape what the product must do. This distinguishes the BA's focus from the project manager, who owns project scope - the work required to deliver the product.

BProject scope

Project scope defines the work required to produce the deliverable and is primarily the responsibility of the project manager, not the business analyst.

CProject charter

The project charter is created by or for the project sponsor and authorizes the project; the business analyst does not own this document.

DBusiness case

The business case justifies the investment in the project and is typically owned by the project sponsor or a business stakeholder, not the business analyst.

Concept tested: Business analyst ownership of product scope

Source: https://www.pmi.org/pmbok-guide-standards/practice-guides/business-analysis

Topics

#Business Analyst responsibilities#Product scope definition#Project artifacts#Roles in projects