CAPM · Question #315

A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation. What…

The correct answer is B. Organize a workshop with the sponsor and major stakeholders. When a community project has a large number of stakeholders, the most effective requirements elicitation approach is to organize a workshop with the sponsor and major stakeholders. Workshops bring the right decision-makers together in a structured, collaborative environment to…

Business Analysis Frameworks

Question

A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation. What should the business analyst do?

Options

  • AEngage a consult ant that is familiar with the community needs.
  • BOrganize a workshop with the sponsor and major stakeholders.
  • CAsk the project coordinator to facilitate some of the workshops.
  • DInvite both internal and external stakeholders to the workshops.

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    75% (21)
  • C
    11% (3)
  • D
    4% (1)

Explanation

When a community project has a large number of stakeholders, the most effective requirements elicitation approach is to organize a workshop with the sponsor and major stakeholders. Workshops bring the right decision-makers together in a structured, collaborative environment to define, prioritize, and validate requirements efficiently. Option A (engaging a consultant) bypasses direct stakeholder input. Option C (delegating facilitation to a coordinator) reduces the BA's control over quality. Option D (inviting all stakeholders) may seem inclusive, but workshops with too many participants-especially external ones without project authority-become unmanageable and unfocused. Focusing on the sponsor and major stakeholders ensures that the people with the most influence and knowledge drive the elicitation process.

Topics

#Requirements Elicitation#Stakeholder Management#Workshops#Business Analysis