nerdexam
PMIPMI

CAPM · Question #314

CAPM Question #314: Real Exam Question with Answer & Explanation

The correct answer is B: Business analyst, project manager, and sponsor. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A key project team member complains about being left out of the communication loop. In order to ensure that each key member is involved, who should review the business analysis communications management plan?

Options

  • ABusiness analyst, project manager, and stakeholders
  • BBusiness analyst, project manager, and sponsor
  • CBusiness analyst and project manager
  • DOnly the business analyst

Topics

#Communications Management#Stakeholder Management#Project Roles and Responsibilities#Business Analysis Planning

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions