CAPM · Question #314
A key project team member complains about being left out of the communication loop. In order to ensure that each key member is involved, who should review the business analysis communications…
The correct answer is B. Business analyst, project manager, and sponsor. The communications management plan should be reviewed by the business analyst (who owns the plan), the project manager (who oversees overall project communications), and the sponsor (who represents executive and business stakeholder interests and can ensure key members are…
Question
Options
- ABusiness analyst, project manager, and stakeholders
- BBusiness analyst, project manager, and sponsor
- CBusiness analyst and project manager
- DOnly the business analyst
How the community answered
(35 responses)- A11% (4)
- B80% (28)
- C3% (1)
- D6% (2)
Explanation
The communications management plan should be reviewed by the business analyst (who owns the plan), the project manager (who oversees overall project communications), and the sponsor (who represents executive and business stakeholder interests and can ensure key members are appropriately included). Including the sponsor ensures the plan reflects business priorities and that no key stakeholders are inadvertently excluded. Option A (including all stakeholders) is too broad and impractical for plan review. Option C omits the sponsor, who has a vested interest in communication effectiveness. Option D is too narrow, limiting review to only the BA.
Topics
Community Discussion
No community discussion yet for this question.