nerdexam
PMIPMI

CAPM · Question #228

CAPM Question #228: Real Exam Question with Answer & Explanation

The correct answer is C: Analogous estimating. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project team member is estimating the cost of an activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

Options

  • ABottom-up estimating
  • BThree-point estimating
  • CAnalogous estimating
  • DParametric estimating

Topics

#Analogous Estimating#Cost Estimation#Estimation Techniques#Project Cost Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions