nerdexam
PMIPMI

CAPM · Question #466

CAPM Question #466: Real Exam Question with Answer & Explanation

The correct answer is A: Milestones. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager is working on a project that is in the planning stage. In order to show the project's progress to the sponsor, the project manager will track significant events in the project life cycle. These events indicate that certain achievements are being met in the project. Which event is being planned?

Options

  • AMilestones
  • BDuration
  • CKickoff
  • DSchedule

Topics

#Milestones#Project Planning#Progress Tracking#Schedule Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions