The correct answer is A: Milestones. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project manager is working on a project that is in the planning stage. In order to show the project's progress to the sponsor, the project manager will track significant events in the project life cycle. These events indicate that certain achievements are being met in the project. Which event is being planned?
Options
- AMilestones
- BDuration
- CKickoff
- DSchedule
Topics
#Milestones#Project Planning#Progress Tracking#Schedule Management