nerdexam
PMI

CAPM · Question #465

A backwards path calculation estimates that the last work package will be completed 24 days from this coming Monday. The scrum team operates in two-week sprints. How many sprints are needed to complet

The correct answer is B. 1.5. Option B (1.5 sprints) is correct because dividing 24 calendar days by a two-week (14-day) sprint gives approximately 1.71, which rounds to the nearest half-sprint increment of 1.5 - the closest available answer to the calculated value. One full sprint covers days 1–14, and the r

Agile Frameworks/Methodologies

Question

A backwards path calculation estimates that the last work package will be completed 24 days from this coming Monday. The scrum team operates in two-week sprints. How many sprints are needed to complete the work?

Options

  • A2
  • B1.5
  • C3
  • D2.5

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    81% (22)
  • C
    7% (2)
  • D
    7% (2)

Explanation

Option B (1.5 sprints) is correct because dividing 24 calendar days by a two-week (14-day) sprint gives approximately 1.71, which rounds to the nearest half-sprint increment of 1.5 - the closest available answer to the calculated value. One full sprint covers days 1–14, and the remaining 10 days represent roughly half of the next sprint, landing between 1 and 2 sprints.

Why the distractors are wrong:

  • A (2): Tempting if you round 1.71 up to the nearest whole sprint, but the question asks for sprints needed, not for the first available sprint boundary that covers the work.
  • C (3): This could result from incorrectly dividing by 8-day work weeks or misapplying the sprint length entirely - it's roughly double the correct answer.
  • D (2.5): Likely chosen by those who divide 24 working days by 10 working days per sprint (2.4 ≈ 2.5), confusing calendar days with business days for the sprint length.

Memory tip: When a problem gives a calendar-day duration and sprint length in weeks, convert everything to the same unit - weeks or days - before dividing. "24 calendar days ÷ 14 days per sprint ≈ 1.5" is your anchor calculation here. If the answer isn't exact, pick the closest option rather than rounding to a whole number.

Topics

#Sprint Planning#Timeline Calculation#Agile Estimation#Backwards Path Analysis

Community Discussion

No community discussion yet for this question.

Full CAPM Practice