PMIPMI
CAPM · Question #465
CAPM Question #465: Real Exam Question with Answer & Explanation
The correct answer is B: 1.5. See the full explanation below for the reasoning.
Agile Frameworks/Methodologies
Question
A backwards path calculation estimates that the last work package will be completed 24 days from this coming Monday. The scrum team operates in two-week sprints. How many sprints are needed to complete the work?
Options
- A2
- B1.5
- C3
- D2.5
Topics
#Agile estimation#Sprint length#Iteration management#Schedule calculation
Community Discussion
No community discussion yet for this question.