nerdexam
PMIPMI

CAPM · Question #465

CAPM Question #465: Real Exam Question with Answer & Explanation

The correct answer is B: 1.5. See the full explanation below for the reasoning.

Agile Frameworks/Methodologies

Question

A backwards path calculation estimates that the last work package will be completed 24 days from this coming Monday. The scrum team operates in two-week sprints. How many sprints are needed to complete the work?

Options

  • A2
  • B1.5
  • C3
  • D2.5

Topics

#Agile estimation#Sprint length#Iteration management#Schedule calculation

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions