nerdexam
PMIPMI

CAPM · Question #292

CAPM Question #292: Real Exam Question with Answer & Explanation

The correct answer is B: Maintaining the product backlog. See the full explanation below for the reasoning.

Agile Frameworks/Methodologies

Question

During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis. What is this an example of?

Options

  • AManaging the cost benefit
  • BMaintaining the product backlog
  • CMonitoring the traceability matrix
  • DManaging the scope

Topics

#Product Backlog#Agile Practices#Requirements Management#Scope Management (Agile)

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions