nerdexam
PMIPMI

CAPM · Question #293

CAPM Question #293: Real Exam Question with Answer & Explanation

The correct answer is B: Escalate this issue to the project sponsor.. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

Options

  • AEscalate this issue to the procurement team.
  • BEscalate this issue to the project sponsor.
  • CEscalate this issue to the chief financial officer (CFO).
  • DEscalate this issue to the project management office (PMO).

Topics

#Budget Management#Escalation#Project Sponsor Role#Risk Response

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions