PMIPMI
CAPM · Question #294
CAPM Question #294: Real Exam Question with Answer & Explanation
The correct answer is B: Predictive. See the full explanation below for the reasoning.
Predictive Plan-Based Methodologies
Question
A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?
Options
- AAdaptive
- BPredictive
- CHybrid
- DKanban
Topics
#Predictive Approach#Project Life Cycles#Upfront Planning#Defined Scope
Community Discussion
No community discussion yet for this question.