nerdexam
PMI

CAPM · Question #294

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the…

The correct answer is B. Predictive. A project with a clearly defined scope and a requirement for advanced upfront planning is best suited for the predictive (waterfall) lifecycle. Predictive approaches are designed specifically for projects where requirements are stable and known at the outset.

Predictive Plan-Based Methodologies

Question

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?

Options

  • AAdaptive
  • BPredictive
  • CHybrid
  • DKanban

How the community answered

(53 responses)
  • A
    2% (1)
  • B
    92% (49)
  • C
    2% (1)
  • D
    4% (2)

Why each option

A project with a clearly defined scope and a requirement for advanced upfront planning is best suited for the predictive (waterfall) lifecycle. Predictive approaches are designed specifically for projects where requirements are stable and known at the outset.

AAdaptive

Adaptive approaches are used when requirements are unclear, evolving, or expected to change frequently, which is the opposite of the described scenario.

BPredictiveCorrect

The predictive lifecycle uses comprehensive upfront planning to define scope, schedule, and cost baselines before execution begins, making it ideal when requirements are well understood and unlikely to change. This approach produces detailed plans - including WBS, schedules, and risk registers - at the start of the project. The scenario explicitly states defined scope and a need for advanced planning, which are the defining characteristics of a predictive approach.

CHybrid

Hybrid approaches combine predictive and adaptive elements and are used when parts of the project have stable requirements and others do not; a fully defined scope does not warrant this complexity.

DKanban

Kanban is a workflow visualization and flow management technique, not a full project lifecycle methodology appropriate for planning a defined-scope project.

Concept tested: Predictive lifecycle selection for defined scope projects

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Predictive Approach#Project Life Cycles#Upfront Planning#Defined Scope

Community Discussion

No community discussion yet for this question.

Full CAPM Practice