PMIPMI
CAPM · Question #295
CAPM Question #295: Real Exam Question with Answer & Explanation
The correct answer is C: Creating a work breakdown structure (WBS). See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project team working on an automobile manufacturing project is detailing the parts needed for a car door design. The door is composed of several parts that have to be developed in sequence, as the frame is needed before other parts can be designed and built. What activity is the team involved in?
Options
- ADeveloping a stakeholder engagement plan
- BDeveloping a communications management plan
- CCreating a work breakdown structure (WBS)
- DIdentifying risks and issues in the project
Topics
#Work Breakdown Structure (WBS)#Scope Management#Decomposition#Project Planning
Community Discussion
No community discussion yet for this question.