CAPM · Question #358

On which type of project life cycle is the deliverable produced trough a series of tolerations considering that the deliverable is completed only after the alliteration?

The correct answer is B. Predictive life cycle. NOTE: The marked answer appears to be incorrect based on PMBOK definitions. An Iterative life cycle (C) is where deliverables are produced through successive refinements over repeated cycles, with the final deliverable only complete after the last iteration - which matches the…

Predictive Plan-Based Methodologies

Question

On which type of project life cycle is the deliverable produced trough a series of tolerations considering that the deliverable is completed only after the alliteration?

Options

  • AIncremental life cycle
  • BPredictive life cycle
  • CIterative life cycle
  • DAdaptive life cycle

How the community answered

(39 responses)
  • A
    5% (2)
  • B
    72% (28)
  • C
    8% (3)
  • D
    15% (6)

Explanation

NOTE: The marked answer appears to be incorrect based on PMBOK definitions. An Iterative life cycle (C) is where deliverables are produced through successive refinements over repeated cycles, with the final deliverable only complete after the last iteration - which matches the question's description. A Predictive (waterfall) life cycle (B) defines scope, time, and cost early and delivers the product through sequential, non-repeating phases - not through iterations. The question's wording ('series of iterations,' 'completed only after the iteration') aligns with the Iterative life cycle. For exam preparation, verify your study materials' definition.

Topics

#Project Life Cycles#Predictive Life Cycle#Deliverable Production#Project Phases