The correct answer is B: Predictive life cycle. See the full explanation below for the reasoning.

Predictive Plan-Based Methodologies

Question

On which type of project life cycle is the deliverable produced trough a series of tolerations considering that the deliverable is completed only after the alliteration?

Options

  • AIncremental life cycle
  • BPredictive life cycle
  • CIterative life cycle
  • DAdaptive life cycle

Topics

#Project Life Cycles#Predictive Life Cycle#Deliverable Production#Project Phases