Project Management Fundamentals and Core Concepts
Question
Which sentence summarizes the salience model?
Options
- AClassifies stakeholders based on assessment their power, urgency and legitimacy
- BA chart in which the Stakeholders are represented as dots according to then level of power and influence
- CA three-dimensional model that ran be useful to engage the stakeholder community
- DClassifies stakeholders and the project team by the impact of their work in the project
Topics
#salience model#stakeholder analysis#stakeholder classification#power urgency legitimacy