CAPM · Question #357

Which sentence summarizes the salience model?

The correct answer is A. Classifies stakeholders based on assessment their power, urgency and legitimacy. The salience model is a stakeholder analysis technique that classifies stakeholders based on three intersecting attributes: Power (ability to impose their will), Urgency (need for immediate attention or time-sensitive interests), and Legitimacy (appropriateness of their…

Project Management Fundamentals and Core Concepts

Question

Which sentence summarizes the salience model?

Options

  • AClassifies stakeholders based on assessment their power, urgency and legitimacy
  • BA chart in which the Stakeholders are represented as dots according to then level of power and influence
  • CA three-dimensional model that ran be useful to engage the stakeholder community
  • DClassifies stakeholders and the project team by the impact of their work in the project

How the community answered

(48 responses)
  • A
    88% (42)
  • B
    2% (1)
  • C
    4% (2)
  • D
    6% (3)

Explanation

The salience model is a stakeholder analysis technique that classifies stakeholders based on three intersecting attributes: Power (ability to impose their will), Urgency (need for immediate attention or time-sensitive interests), and Legitimacy (appropriateness of their involvement). Answer A correctly summarizes all three dimensions. Answer B describes a power/influence grid. Answer C is a vague description. Answer D describes an impact-based classification. The salience model is particularly useful for complex stakeholder environments where prioritizing engagement is critical.

Topics

#salience model#stakeholder analysis#stakeholder classification#power urgency legitimacy