The correct answer is A: Classifies stakeholders based on assessment their power, urgency and legitimacy. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

Which sentence summarizes the salience model?

Options

  • AClassifies stakeholders based on assessment their power, urgency and legitimacy
  • BA chart in which the Stakeholders are represented as dots according to then level of power and influence
  • CA three-dimensional model that ran be useful to engage the stakeholder community
  • DClassifies stakeholders and the project team by the impact of their work in the project